In Pit Crusher Conveyor

Expending over 97,000 work hours in eight months and finishing 30 days ahead of schedule, ames crews constructed the 120-foot tall in-pit crusher station in kennecott bingham canyon mine, the largest open pit copper mine in the worldhe crusher station included a dump pocket for 350-ton haul trucks, crusher surge hopper, structural and mechanical installation of a belt feeder, three transfer.